Tribunal cancels Kenya coal power project licence

Thursday June 27 2019
PLANT

Construction site for the Lamu coal plant in Kenya's coastal region. PHOTO | FILE | NATION MEDIA GROUP

By ABIUD OCHIENG

Kenya's National Environment Tribunal has cancelled the licence issued to Amu Power Company Ltd for setting up a coal plant, saying it was done unprocedurally.

Anti-coal activists have been pushing for the government to focus on setting up clean energy projects instead of coal.

Organisations, notably Save Lamu, Lamu Youth Alliance and Lamu Marine Forum have been loudly opposed to the proposed Sh200 billion coal power plant.

ILLEGAL LICENCE

The tribunal Wednesday said that the National Environment Management Authority (Nema) issued the environmental impact assessment licence to Amu Power without following the law.

The tribunal faulted the coal project for omitting engineering plans and key facts of the project from public participation as well as failure to take account of the Climate Change Act.

Advertisement

Nema was faulted for granting the coal project a licence that appeared to be generic and not specific to the project.

Katiba Institute had filed the case on behalf of the Save Lamu lobby group. Nema and Amu Power were listed as respondents.

The tribunal, led by Mohamed Balala, said that should Amu Power consider proceeding with the project, it will have to carry out a fresh environmental impact assessment in accordance with the law and comply with all the necessary laws.

Following the ruling, Amu Power CEO Cyrus Kirima said that the firm had taken note of the concerns raised in the ruling and was committed to working with stakeholders to ensure that all matters are addressed.

“Amu Power’s goal is to improve the lives of the communities in Lamu County; employment creation, infrastructure development, upskilling of the youth and the provision of affordable energy generated from coal power.

“A goal which we believe is in the interest of all, both at the county and national level,” Mr Kirima said in a press statement sent to newsrooms.

The project, set to be implemented by Amu Power, a consortium of Gulf Energy and Centum Investment, is to be established at Kwasasi village in Hindi Division, Lamu West.

Some 975 acres of land had already been set aside for the project which is expected to generate 1,050 megawatts of power upon completion.

Last week, the government condemned critics of the power plant terming them, “enemies of progress”.