Dar airport to handle over 30 planes an hour

Share Bookmark Print Email
Email this article to a friend

Submit Cancel
Rating
The Julius Nyerere International Airport. Houses in the nearby Kipawa suburb have been demolished to pave the way for expansion of Terminal One and Two of the airport. Photo/LEONARD MAGOMBA

The Julius Nyerere International Airport. Houses in the nearby Kipawa suburb have been demolished to pave the way for expansion of Terminal One and Two of the airport. Photo/LEONARD MAGOMBA 

By WILFRED EDWIN  (email the author)
Send Cancel

Posted Monday, March 1 2010 at 00:00

The modernisation of JK Nyerere International Airport, to be completed in July this year, will enable it to handle more than 30 planes an hour, up from the current 11.

Terminal One and Two of the busiest airport in Tanzania are currently being expanded, in a $56 million project — a combination of a loan from the Netherlands and funds from the Tanzanian government.

Infrastructure Development Minister Shukuru Kawambwa, who visited the airport last week, said the airport will handle larger aeroplanes and more passengers.

Dr Kawambwa said the two terminals are currently congested, since they were designed to handle only 1.2 million passengers a year but are now handling up to 1.5 million.

Tanzania’s aviation industry is growing by 14 per cent every year.

At Terminal Two, construction of a new taxiway, parallel to the old one, is expected to be complete by July.

Tanzania Airport Authority manager Proper Tesha says the new taxiway is built to the level of a runway — meaning it is strong enough to be used as a runway during emergencies.

A new VIP lounge that is currently under construction near Terminal Two is expected to be completed in April, in time for the arrival of world leaders for the Economic Forum for Africa that is scheduled to be held in Dar es Salaam for the first time in May.

The VIP building is being funded by China Sonangol International to the tune of $6 million.

It will accommodate more than 75 guests and still have room to spare, compared with the one-room VIP lounge at Terminal Two.

The VIP conference room can accommodate more than 36 people.

On completion of another project to Terminal 3, within the same area, the JK Nyerere International Airport will be able to handle seven million passengers a year.

This will enable it to compete with other regional airports such as Nairobi’s Jomo Kenyatta International Airport, officials say.

Dr Kawambwa says construction of buildings for Terminal Three will start soon.

The terminal will house international passenger lounges, commercial complexes, hotels and a fuel station, which is currently at terminal one.

flashad
1 | 2 Next Page »

Add a comment (0 comments so far)

IN PICTURES: Kenya census report

A section of Uhuru Park crowds witnessing the promulgation of the constitution. Photo/CHRIS OMOLLO

IN PICTURES: Promulgation Day

Simon Gitau, a Kenya Wildlife Service warden (front) and Mr Simon Wachira (in yellow) lead a group of 22 people to climb Mt Kenya on August 25, 2010. The Kenyan flag will be mounted at Batian point while the new constitution will be cemented at point Lenana on Friday. Photo/ JOSEPH KANYI

IN PICTURES: Mountain climbing for a new dawn

Kenya's David Lekuta Rudisha poses for photographers after winning the men's 800m competition during the ISTAF (Internationales Stadionfest) IAAF World Challenge on August 22, 2010 in Berlin. He set a new world record. AFP PHOTO/JOHANNES EISELE

IN PICTURES: Rudisha at Berlin IAAF World Challenge